This contract involved the design & build of a new five storey 2850m2 building housing a 68 bedroom Travelodge Hotel and 350m2 of retail shell along with 1100m2 of high quality public realm in Telford Town Centre during 2017-18. The project was secured through competitive tender and following this was delivered with novation of the client’s architect.

CFA piling with pile caps was required for foundations and a 350mm reinforced concrete raft slab was cast.

The ground floor used a steel frame with podium deck and the upper floors were a closed system timber frame with acoustic floating floors. Composite flat panel cladding was Kingspan Benchmark with a trapezoidal built-up system roof and aluminium double glazed windows were used.

Off-site manufactured bathroom/shower pods were installed and all bedrooms have air conditioning with air-source heat pumps. High efficiency boilers and two CHP plants provide hot water and electricity. Two pre-cast concrete lift shafts were constructed for personnel lifts.

Externally 1100m2 of new public realm used Irish Blue Limestone and a 25 jet programmable water fountain has been installed complete with feature lighting wands and misting systems. Planters, benches etc. completed the external works.